Key Milestones
2023
July
Phase 1B I-25 S-Curve Area Study Kickoff
2023
Summer ― Fall
Preliminary Data Gathering, Develop
Purpose & Need, Develop Wide Range of Ideas
2023
Nov. – Dec.
Public Comment Period from Nov. 15 to Dec. 17 to Gather Input on the Purpose & Need/Universe of Ideas Including Public Meeting on Nov. 15
2023/2024
Fall ― Winter
Evaluate Ideas, Develop Options and Screening Criteria, Assess Options
2024
Spring
Public Comment Period from April 24 to June 10 to Gather Input on the Alignment and Interstate Exchange Options Considered, those Eliminated, and the Options Recommended to Advance, Including Second Public Meeting on April 24.
2024
Spring ― Summer
Combine Options into Alternatives, Screen Alternatives, and Identify the Preferred Alternative
2024
Fall
Host Public Involvement Event(s)
to gather input on Alternatives and Preferred Alternative
2024/2025
Fall― Winter
Draft the Environmental Document
2025
Spring
Hold Public Involvement Event(s) to Gather Input on the Preferred Alternative and the Draft Environmental Document
2025
Spring ― Fall
Evaluate Public Comments, NMDOT
and Federal Reviews
2025
Fall
Final Environmental Decision Document