Key Milestones

2023
July

Phase 1B I-25 S-Curve Area Study Kickoff

2023
Summer ― Fall

Preliminary Data Gathering, Develop

Purpose & Need, Develop Wide Range of Ideas

2023
Nov. – Dec.

Public Comment Period from Nov. 15 to Dec. 17 to Gather Input on the Purpose & Need/Universe of Ideas Including Public Meeting on Nov. 15

2023/2024
Fall Winter

Evaluate Ideas, Develop Options and Screening Criteria, Assess Options

2024
Spring

Host Public Involvement Event(s) to gather input on Options and the Screening Process

2024
Spring ― Summer

Combine Options into Alternatives, Screen Alternatives and Identify the Preferred Alternative

2024
Summer

Host Public Involvement Event(s)
to gather input on Alternatives and Preferred Alternative

2024/2025
Fall― Winter

Draft the Environmental Document

2025
Spring

Hold Public Involvement Event(s) to Gather Input on the Preferred Alternative and the Draft Environmental Document

2025
Spring ― Fall

Evaluate Public Comments, NMDOT
and Federal Reviews

2025
Fall

Final Environmental Decision Document

What Does Each Milestone Mean?